AILoadmapAI gigawatts, campus by campus
← Map · All projects

Meta-QTS Hillsboro 2 · Hillsboro, OR

Last change recorded — · Last checked 2026-10-05

OwnerMeta
UsersMeta
IT power, end of 2026180 MW
Planned end state180 MW
First power2023-08-02
Build-out completeno further build-out tracked
Power pathNo data yet
Binding stepNo data yet
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersPortland General Electric

Recorded readiness — 0 of 5 applicable milestones have a dated public record

○ Land○ Permits○ Grid supply· Generation○ Water· Financing○ Construction

Gate to first power — target 2023-08-02 (estimate) · path: unknown, generic steps assumed · each step must finish its lead time before the target

0 of 0 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

No dated steps on record.

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2023-08-02 First powerFirst power (Epoch) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2021-04-01—First signs of site land clearing appear on satellite imagery.
2023-04-29—Satellite imagery shows Building 3 and 4 cooling start to go on.
2023-08-0245 MWSatellite imagery shows Building 2 and 3 cooling nearing completion and Building 4 cooling install continues. We believe Building 1 is operational now due to the lack of construction equipment on or immediately around th
2024-11-08180 MWWe believe Buildings 2, 3, and 4 are operational due to the absence of construction vehicles and completed parking lots/concrete around the facilities. There is also a vehicle presence in the parking lot similar to the l
2025-04-14180 MWAll four buildings are operational
2026-04-17180 MWAll four buildings are operational.

Recorded fact The site is energized.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): QTS Hillsboro 2 data center announcement · QTS and Meta sign an agreement with PGE for a 120MWac solar installation

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id meta-qts-hillsboro-2; include the row and a source link).