AILoadmapAI gigawatts, campus by campus
← Map · All projects

Google Papillion · Papillion, NE

Last change recorded — · Last checked 2026-10-05

OwnerGoogle
UsersGoogle DeepMind
IT power, end of 2026237 MW
Planned end state237 MW
First power2023-01-23
Build-out completeno further build-out tracked
Power pathNo data yet
Binding stepNo data yet
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersOmaha Public Power District (verify)

Recorded readiness — 0 of 5 applicable milestones have a dated public record

○ Land○ Permits○ Grid supply· Generation○ Water· Financing○ Construction

Gate to first power — target 2023-01-23 (estimate) · path: unknown, generic steps assumed · each step must finish its lead time before the target

0 of 0 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

No dated steps on record.

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2023-01-23 First powerFirst power (Epoch) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2020-03-04—Land clearing begins for Building 1 of expansion.
2022-10-16—Building 2 under construction. Building 3 begins construction.
2023-01-2379 MWBuilding 1 assumed operational due to vapor from cooling towers. Building 2 4/7 cooling towers installed. Building 3 roof complete coverage but unfinished.
2024-02-1579 MWBuilding 2 assumed operational due to vapor from cooling towers. Building 3 5/7 cooling towers installed.
2024-08-03237 MWBuilding 3 looks operational.
2025-11-03237 MWLand cleared for Building 4 and 5.
2026-05-04237 MWBuilding 4 shell mostly complete, Building 5 steel framing is underway.

Recorded fact The site is energized.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Draft basis of air permit with details of cooling towers · 2025 Environmental Report

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id google-papillion; include the row and a source link).