AILoadmapAI gigawatts, campus by campus
← Map · All projects

Google Hamina · Hamina, Finland

Last change recorded — · Last checked 2026-10-05

OwnerGoogle
UsersGoogle
IT power, end of 2026300 MW (est.)
Planned end state300 MW
First power2011-09-01
Build-out complete2026-12-31 (est.)
Power pathGrid supply
Binding stepNo data yet
First power vs announcedon time (announced 2011-09-01)
Full build-out vs announcedNo announced date on record
Utility / power partnersFingrid

Operating since 2011; about 300 MW planned with Building 7 due in 2026, part of Google's €13bn Finland commitment for 2027-2028 (Hamina, Kajaani, Muhos, Vaala). Current MW is a placeholder. · source ● primary, confidence medium

Recorded readiness — 2 of 5 applicable milestones have a dated public record

● Land 2009-01○ Permits○ Grid supply· Generation○ Water· Financing● Construction 2010-01

Gate to first power — target 2011-09-01 (announced) · path: Grid supply · each step must finish its lead time before the target

0 of 0 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2010-06-01 (15 mo before)13 mo before (n=26)2009-01-01contextCampus announced (reported) · ●
Construction started (context)2009-09-01 (24 mo before)29 mo before (n=15)2010-01-01contextConstruction start (reported) · ●
Full build-out complete (context)2012-09-01 (-12 mo before)—2026-12-31 plancontextFull build-out (announced plan) · ●

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2009-01-01 Site securedCampus announced (reported) · ●
2010-01-01 Construction startedConstruction start (reported) · ●
2011-09-01 First powerFirst phase online (reported) · ●
2026-12-31 plan Full build-out completeFull build-out (announced plan) · ●

Build-out timeline (announced phases from public reporting; rows after today are plans)

2011-09-01300 MWFirst phase online (reported)
2026-12-31 est.300 MWFull build-out (announced plan)

Recorded fact The site is energized.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources: Google deepens commitment to Finland with €13bn investment

Campus outside the Epoch AI dataset: facts from the public reporting linked above (tools/campuses.csv), coordinates hand-entered. Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id google-hamina; include the row and a source link).