AILoadmapAI gigawatts, campus by campus
← Map · All projects

CDC Wagga Wagga Campus · Wagga Wagga, NSW, Australia

Last change recorded — · Last checked 2026-10-05

OwnerCDC Data Centres
Users—
IT power, end of 20260 MW
Planned end state1.4 GW
First powerno date yet
Build-out completeno date yet
Power pathGrid supply
Binding step 3 required steps without a date
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersTransgrid

A$15bn four-building campus of up to 1.4 GW on 103.8 ha south of Wagga Wagga, fed by a dedicated connection to Transgrid's 330 kV substation 1.3 km away, with 384 diesel generators and 13 MW rooftop solar; development application lodged September 2026. · source ◐ secondary, confidence high

Recorded readiness — 1 of 6 applicable milestones have a dated public record

● Land 2026-09○ Permits○ Grid supply· Generation○ Water○ Financing○ Construction

Gate to first power — target unknown · path: Grid supply · each step must finish its lead time before the target

0 of 3 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)— (15 mo before)13 mo before (n=26)2026-09-30contextCampus announced (reported) · ◐
Grid supply agreed— (9 mo before)7 mo before (n=11)no public dateno public date · would need to be done by —No date on record
Substation and lines energized— (2 mo before)15 mo after (n=1)no public dateno public date · would need to be done by —No date on record
Building ready for IT— (0 mo before)2 mo after (n=7)no public dateno public date · would need to be done by —No date on record
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2026-09-30 Site securedCampus announced (reported) · ◐

Build-out timeline (announced phases from public reporting; rows after today are plans)

No dated timeline on record.

Recorded fact No public date for grid supply agreed, substation and lines energized, building ready for it.

Calculated requirement No first-power target on record, so no deadlines can be computed.

Sources: Australia's CDC plans gigawatt-scale campus in Wagga Wagga (DCD)

Campus outside the Epoch AI dataset: facts from the public reporting linked above (tools/campuses.csv), coordinates hand-entered. Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id cdc-wagga-wagga-campus; include the row and a source link).