AirTrunk JHB1 · Iskandar Puteri, Johor, Malaysia

Last change recorded — · Last checked 2026-10-05

OwnerAirTrunk
Users—
IT power, end of 202650 MW
Planned end state150 MW
First power2024-07-30
Build-out completeno further build-out tracked
Power pathGrid supply
Binding stepNo data yet
First power vs announcedon time (announced 2024-07-30)
Full build-out vs announcedNo announced date on record
Utility / power partnersTNB

150 MW campus launched 2024-07-30 with initial phases over 50 MW, 18 months after announcement; JHB2 (270 MW) follows, and JHB3-4 (280 MW, announced 2026-04-30) take Malaysia above 700 MW; US$2.3bn green financing 2026-07-29 and Malaysia's first renewable VPPA for a data center (ib vogt, 2026-07-01). · source ◐ secondary, confidence high

Recorded readiness — 2 of 6 applicable milestones have a dated public record

● Land 2023-01○ Permits○ Grid supply· Generation○ Water○ Financing● Construction 2023-03

Gate to first power — target 2024-07-30 (announced) · path: Grid supply · each step must finish its lead time before the target

0 of 0 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2023-04-28 (15 mo before)13 mo before (n=26)2023-01-15contextCampus announced (reported) · ◐
Construction started (context)2022-07-28 (24 mo before)29 mo before (n=15)2023-03-01contextConstruction start (reported) · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2023-01-15 Site securedCampus announced (reported) · ◐
2023-03-01 Construction startedConstruction start (reported) · ◐
2024-07-30 First powerFirst phase online (reported) · ◐

Build-out timeline (announced phases from public reporting; rows after today are plans)

2024-07-3050 MWFirst phase online (reported)

Recorded fact The site is energized.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources: AirTrunk launches Johor data center (DCD)

Campus outside the Epoch AI dataset: facts from the public reporting linked above (tools/campuses.csv), coordinates hand-entered. Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id airtrunk-jhb1; include the row and a source link).